Buyer guide · 7 min read ·
Buy America, Build America Buy America and country of origin for transformers: what public buyers ask for and how to answer
Three different federal rules get called "Buy America" in solicitations. They apply to different funding, use different tests and require different paperwork. This guide separates them in general terms, so a purchasing office can write the right requirement and a supplier can answer it precisely. It is general guidance, not legal advice; your counsel and the awarding agency decide what applies to a given grant.
Three rules, three scopes
| Rule | When it applies | Test, in general terms |
|---|---|---|
| Buy American Act (BAA, 1933) | Direct federal purchases above the micro-purchase threshold | Domestic end product: manufactured in the U.S. with a domestic component cost above the threshold set by regulation (65 % from 2024, rising to 75 % in 2029); price preference rather than prohibition |
| Buy America (FTA, FHWA, FRA) | Transit, highway and rail projects with those agencies' funds | Steel, iron and manufactured products produced in the U.S.; agency-specific component rules; waivers published by each agency |
| Build America, Buy America Act (BABA, IIJA 2021) | Any federal financial assistance for infrastructure after May 14, 2022, including water, energy and broadband grants | Iron and steel 100 % U.S.; manufactured products made in the U.S. with more than 55 % U.S. component cost; construction materials with their own rules; waivers by agency |
Thresholds and waivers change. Confirm the current text with the awarding agency before writing a specification.
A municipal utility buying with its own revenue is usually under none of these; its own procurement code and any state preference apply. The rules enter when a grant, a loan or a federal program pays for part of the equipment.
What a buyer should ask for
- State which rule applies and cite it, with the funding source. "Buy America compliant" without a citation cannot be answered honestly.
- Ask for a country-of-origin statement per unit covering final assembly and the principal components: core steel, windings, tank, bushings and fluid.
- Ask whether the manufacturer certifies the unit as a domestic end product or manufactured product under the cited rule, or whether a waiver is being relied on.
- Require the statement as a signed submittal, not a checkbox on a bid form.
How we answer
Our submittal includes a country-of-origin statement for the unit and its principal components, signed by the supplier, with the manufacturer named. Where an offered unit is built in Mexico or Korea, the statement says so and the quote notes which rules it does and does not satisfy. Where a solicitation requires a domestic product under BABA or Buy America, we quote a U.S. plant or say in the first reply that we cannot meet the requirement. The origin statement is part of the standard submittal package listed on the compliance page.
A unit that qualifies for duty-free entry under USMCA is still a Mexican-origin product for Buy America purposes. Trade preference and domestic-content rules are separate questions.
Tariffs and origin on the invoice
Section 232 duties on steel and aluminum content, and country-specific tariffs, are priced into our quotes at the rate in force on the quote date, with the assumption stated. If duties change between quote and shipment, the quote says how the difference is handled. Customs entry and the origin declared to CBP are our responsibility as importer; the buyer receives a clean domestic delivery, FOB destination.
Frequently asked.
- Is a transformer a 'manufactured product' or 'iron and steel' under BABA?Agencies have generally treated transformers as manufactured products, subject to the 55 % domestic component cost test. Confirm with the awarding agency's guidance.
- Does assembly in the U.S. from imported parts count?Under BABA, final manufacture must be in the U.S. and the domestic component cost must exceed 55 %. Assembly alone does not settle it.
- Can a utility apply for a waiver?Waivers are issued by the federal agency, usually for non-availability or unreasonable cost; the grantee requests them. Lead-time non-availability waivers for transformers have been granted by some agencies.
- What if the solicitation says 'Buy American preferred'?That is a price preference, not a prohibition. Ask the buyer for the preference percentage so offers can be compared.
- Do you provide the origin statement before award?Yes. It is in the submittal package with the quote, so the evaluation can use it.