Transformer RFQ checklist for public utilities: what to include to receive comparable quotes

Most unusable quotes trace back to a request that left something open: no delivery point, no required date, no standard cited. Suppliers fill the gaps differently and the purchasing office cannot compare. This checklist is what an RFQ for distribution transformers or switchgear should contain, in the order a supplier reads it. It fits on one page.

The product

  1. Product type and quantity per line: for example 12 × three-phase pad-mounted, 500 kVA; 40 × single-phase pole-mounted, 25 kVA.
  2. Primary voltage and connection, secondary voltage, voltage class and BIL, written as the standard writes them.
  3. Loop or radial feed, fusing, switching and accessories, or the reference to your material standard that settles them.
  4. The standards: IEEE C57.12.00, the product standard (C57.12.34, C57.12.26, C57.12.20 or C37.74), ANSI C57.12.28 for enclosures, DOE 10 CFR 431 for efficiency.
  5. Loss evaluation factors (A and B, in $/W) if you evaluate on total owning cost, and the tolerance and penalty on guaranteed losses.
  6. Insulating fluid, finish color and nameplate requirements if they differ from the standard defaults.

The commercial terms

  1. Delivery point: street address, receiving hours, whether a forklift or crane is available, and any site constraints for a flatbed.
  2. Freight basis: FOB destination, freight prepaid and allowed, is the usual request from public buyers; state who off-loads.
  3. Required date or acceptable delivery window, and whether partial shipments are accepted.
  4. Price validity you need (30, 60, 90 days) and whether you want firm pricing for an annual agreement.
  5. Payment terms: Net 30 from invoice is standard for public buyers; say if you pay on receipt and acceptance or on invoice.
  6. Warranty expectation: term, start point (shipment or energization) and who administers claims.
  7. Evaluation method and award basis: lowest price meeting specification, total owning cost, or best value with stated criteria.

The paperwork

Ask forWhyWhen
DOE certification and guaranteed losses per modelEvaluation and complianceWith the quote
Outline and nameplate drawingsPad or pole design, approval before manufactureWith the quote or within two weeks of order
Per-unit factory test report (IEEE C57.12.90)Acceptance against guaranteesWith each shipment
Country-of-origin statementFunding rules, recordsWith the quote
W-9, certificate of insurance, vendor registrationVendor file, paymentWith the quote or at award
Conflict-of-interest and other local formsYour procurement codeAt award
ONE FILE, ONE EMAIL

Send the RFQ as a single PDF with the material standard attached and a single reply address. Suppliers answer faster and questions reach the right person. Our submittal package is listed on the compliance page and the purchase routes on the how to buy page.

What we return

A written quote within one business day for standard ratings: unit prices, named manufacturer, lead time in weeks from approved drawings, freight basis, validity, exceptions to your standard line by line, and the submittal package above. If we cannot meet a line of the specification, the quote says so in the first reply.

QUESTIONS WE ARE ASKED

Frequently asked.

  • How many suppliers should receive an informal RFQ?Three is the usual practice under small-purchase rules; check your code. More than five rarely improves the result and slows the answers.
  • Should the RFQ ask for a sample unit?For a new manufacturer on a large program, a first-article inspection or a factory visit is more useful than a sample.
  • Can a supplier quote an alternate rating?Only if the RFQ allows alternates and says how they will be evaluated. Otherwise the quote should follow the request exactly.
  • What is the minimum price validity to ask for?Sixty days covers most award cycles. Ask for ninety if your governing body meets monthly.
REQUEST A QUOTE

Send ratings, quantities and a delivery point.

We reply within one business day with price, lead time from a named manufacturer and the submittal package described on the compliance page.